 NO.

 SUBJECT

ACHIEVEMENT %

1.

To process an application for Building Plan Approval within 21 days for OSC Committee Meeting

 100 %

2.

Provide review for Application Certificate of Fitness within 14 days

100 %

3.

To process Certificate of Fitness Approval within 3 days after E Form Acceptance Endorsement been made

 100 %

4.

To process Application for Residences Additional Plan approval within 24 hours if completed

 100 %

5.

To process Equivalent Plan Approval Application within 1 hour if completed

100 %

6.

To process an Application for Permit approval of minor works within 1 hour if completed

 100 %